Insurance related works for flood reinstatement works including strip out to existing decorative finishes throughout club, reform/lay damaged concrete slab, new floors and finishes, new stud walls, doors/frames, new toilet and w.c facilities, electrical and plumbing works, decking platform, sub ground drainage works, render and redecoration, security system, external hard-standings/paths and flood protection works
Contract value
—
£138,500
Programme
—
15 weeks
Contract
—
JCT MW 2016
Case Study: Waterfall Tennis Club, 100 Pymmes Green Road, New Southgate, N11 1DD C/O Sedgwick Insurance
Full Contract Administrator, Project Management and Principal Designer role under CDM Regs 2015 provided.
Initial site inspection to report back to client/insurer on observations, agree brief and insurable/betterment works.
Collation of Specification of reinstatement works including working drawings, issue to tender, tender queries, tender report on costs + recommendation
Client. Insurer and contractor liaison
Attendance at and minuting pre-start meeting, review of progress/quality of works from weekly inspections, monthly progress meetings, managed and processed /certified contractor valuations and managed budgets and programme, including Liaison with client and insurer and stakeholders.
Principal Designer role, CDM Regs 2015 compliance and liaison with Client and Principal Contractor